Challenging an incorrect Project Manager assessment under NEC

When assessments ignore Defined Cost or misapply the Accepted Programme, contractors must respond with contract-led challenges.

Incorrect assessments under NEC

Project Manager assessments can be challenged where they misapply the contract, ignore valid cost evidence, take an incorrect programme position or fail to assess the compensation event in accordance with the contract.

Key response points

  • Identify the assessment basis used.
  • Compare it against the contractual mechanism.
  • Evidence the correct Defined Cost and programme effect.
  • Keep the challenge commercial, concise and defensible.